Lot of rushed progress in the second session. We finished the side arms that stabilizer the lifter while it is lifting. To release, it is really touchy. A bump on the side will release them. We made adjustment to the robot so it will meet the size requirement. It fixes inside of our case. This ensures that it is in the requirements since it was built to be one sixteenths of an inch under 18 in.. We tightened all of the bolts and nuts that were loosen and reinforced the forklift system. The kit of items that we are to take is finished as well as the B.O.M(Bill Of Materials). All there is left to do is the programming award requirements which should be only printing out the code. Since the rush is over, more about the team will be posted in my free time or at the next session. Until then, wish us luck(i have a feeling that we will need it). :)